Carisbrooke saves money with ‘DIY’ ballast water system installation
PRESS RELEASE – UK shipowner Carisbrooke Shipping has adopted a novel approach to ballast water treatment (BWT) compliance, installing its latest two systems during normal operations and with its own crewmembers, ensuring zero downtime and maximum efficiency and earnings.
The shipping company, which controls a fleet of general cargo vessels from its base in the Isle of Wight, has just completed ‘DIY’ installations onboard the 8690 dwt Vectis Falcon and Vectis Eagle.
Carisbrooke signed a Ballast Water Treatment frame agreement with Optimarin in 2016, shortly before the Norwegian headquartered specialist became the first supplier in the world to receive full USCG approval for its UV-based Optimarin Ballast System (OBS). Carisbrooke has since completed the installation of six systems, four during scheduled dry dockings and two in a more unconventional way.
“The Vectis ships trade frequently in US waters”, explains captain Simon Merritt, senior fleet manager at Carisbrooke. “Because US compliance dates are earlier than those of IMO, we had to install the systems before the vessels´ next scheduled docking, so we contacted manufacturer Optimarin to discuss alternatives.”
It quickly became apparent that the crew could do it themselves, installing the OBS during scheduled operations, with zero disruption. “The benefits of that were obviously very compelling, so we thought ‘yes, let’s go for it’”, Merritt says.
Giant jigsaw
The project required thorough 3D scanning of the engine room, conducted by Goltens, to provide the measurements that would dictate the positioning of the modular Optimarin BWT unit. Carisbrooke then contacted a Polish manufacturer to make the required piping and foundations.
“We made sure we had crewmembers with the mechanical and electrical competency to take on this kind of project, but it really wasn’t that technically challenging”, says Merrit. “I’d compare it to putting together a giant jigsaw. As long as you have all the pieces you need – and that’s where you have to get the pre-work right – then it’s just a question of focusing on the task at hand.”
Bottom-line benefits
The ‘DIY’ approach saved Carisbrooke both time and money. The biggest advantage was the ability to maintain scheduled operations and provide uninterrupted services. “Zero downtime means zero lost earnings”, Merritt says.
By conducting the installation internally expenses were minimal compared to dry dock charges or port installation with third party contractors.
“To put this into context: When we conducted the first installations the costs for the pipework and foundation packages were four times what we paid with our own hand-picked supplier. We paid a grand total of EUR 22,000 for the entire package. A very significant saving.”
morenews
Project Cargo Summit 2024 programme takes shape
Excitement is building for the Project Cargo Summit 2024 in Bilbao, Spain! The dates are locked in (September 17th and 18th), the speaker list is filling up fast, and preparations are underway to make the “Project Cargo Summit 2024: Mega Cargo, Mega Solutions” an unforgettable event.
Project Cargo Summit 2024 registrations open
The time has come, we have opened registrations for this year’s edition of the Project Cargo Summit. As it was previously unveiled, the Port of Bilbao will be our host on September 17 and 18. There have been some changes since the announcement.
Project Cargo Summit goes to Bilbao
Following the successful outing in Bremen in 2023, ProMedia and its Project Cargo Summit team have turned their sights to a new adventure and have partnered with the Port of Bilbao. So for the 2024 edition of the Project Cargo Summit, project cargo, breakbulk and heavy lift industry specialists will gather in Bilbao for two… Read more ›